BS 1139-6-2022 pdf free downlaod.Metal scaffolding Part 6: Prefabricated tower scaffolds outside the scope of BS EN 1004, but utilizing components from such systems — Specification.
This part of BS 1139 specifies requirements for the structural design of prefabricated tower scaffolds utilizing components from mobile access and working towers specified in BS EN 1004-1 but in
configurations that are outside of the scope of that standard.
These configurations include:
a) high level tower scaffolds outside the maximum height limits of BS EN 1004-1;
b) tower scaffolds with more than one working platform at one time;
c) large deck tower scaffolds;
d) linked tower scaffolds;
e) cantilever tower scaffolds;
f) stepped tower scaffolds;
g) tower scaffolds used as a means of access to another place;
h) non-mobile towers built on base plates instead of castors; and i) tower scaffolds subject to wind loads greater than 0.1 kN/m 2 .
NOTE Towers with wind loads up to 0.1 kN/m 2 are specified in BS EN 1004-1. Where a prefabricated tower scaffold might be subject to wind in excess of 0.1 kN/m 2 , and it cannot be dismantled or moved to avoid these winds,suitable wind design criteria can be found in this British Standard.
This British Standard does not cover prefabricated tower scaffolds using guys as a method of stabilization.
This British Standard does not cover prefabricated towers intended to be lifted.
2 Normative references
The following referenced documents are indispensable for the application of this document. For dated references, only the edition cited applies. For undated references, the latest edition of the referenced document (including any amendments) applies.
Standards publications
BS 1139-1.2, Metal scaffolding – Part 1: Tubes – Section 1.2 Specification for aluminium tube
BS 1139-2.2, Metal scaffolding – Part 2: Couplers and fittings – Section 2.2 Couplers and fittings outside the scope of BS EN 74 – Requirements and test methods
BS 5975, Code of practice for temporary works procedures and the permissible stress design of falsework BS 8539, Code of practice for the selection and installation of post-installed anchors in
concrete and masonry
BS EN 74 (all parts), Couplers, spigot pins and baseplates for use in falsework and scaffolds
BS EN 1004-1, Mobile access and working towers made of prefabricated elements – Materials,dimensions, design loads, safety and performance requirements
BS EN 1993-1-1, Eurocode 3: Design of steel structures – Part 1-1: General rules and rules for buildings
BS EN 1995-1-1, Eurocode 5: Design of timber structures – Part 1-1: General – Common rules and rules for buildings
BS EN 1999-1-1, Eurocode 9: Design of aluminium structures – Part 1-1: General structural rules
BS EN 12810-1, Facade scaffolds made of prefabricated components – Part 1: Product specifications
BS EN 12811-1, Temporary works equipment – Part 1: Scaffolds – Performance requirements and general design
BS EN 12811-2, Temporary works equipment – Part 2: Information on materials
BS EN 13374, Temporary edge protection systems – Product specification – Test methods
3 Terms and definitions and symbols
3.1 Terms and definitions
For the purposes of this part of BS 1139 the terms and definitions given in BS EN 1004-1 together with the following apply.
3.1.1 alteration
planned change in the design from one permitted configuration to another which is specified in the user instructions or assembly use and dismantling plan
3.1.2 anchor
manufactured device for achieving a connection between a tie and the base material of the supporting structure
[SOURCE: BS 8539:2012+A1:2021, 3.1.2, modified]
NOTE This is also known as a fixing or fastener. In CEN technical specifications the terms “anchor” and “fastener” are used synonymously.
3.1.3 application
task for which the prefabricated tower scaffold was assembled
3.1.4 bay
section between uprights of a prefabricated tower scaffold through the entire length or width of the tower when viewed in elevation
NOTE Examples of a bay can be seen in Figure 1.
3.1.5 cantilever platform
working platform which projects outwards from the side or end of, and is supported by, the prefabricated tower scaffold
NOTE An example of a cantilever platform can be seen in Figure 2.
3.1.6 cladding
material normally intended to provide weather and dust protection, typically sheeting or netting
NOTE Where cladding of the working scaffold is required, this standard assumes that the scaffold will be clad with either netting or sheeting.
3.1.7 intermediate platform
platform in a mobile access and working tower that is not a working platform
[SOURCE: BS EN 1004-1:2020, 3.22]
NOTE An intermediate platform is used as a place to stand when installing or removing components of the tower when assembling, altering or dismantling the tower, or as a place to stand when ascending or descending the tower.
3.1.8 maximum wind load
maximum out of service horizontal load caused by wind
3.1.9 netting
pervious cladding material
3.1.10 non-standard configuration
configuration of a prefabricated tower scaffold designed for a specific site and supplied with an assembly, use and dismantling plan
3.1.11 prefabricated tower scaffold
temporary works structure made up from prefabricated components which have their dimensions fixed by the design
NOTE 1 Prefabricated tower scaffolds include components used in mobile access and working towers specified in BS EN 1004-1 but in one or more configurations that are outside the scope of that standard.
NOTE 2 It might:
a) be rendered moveable by the fitting of castor wheels or other mobility devices in contact with the supporting surface at the base, or be rendered static by the fitting of base plates in contact with that surface;
b) be structurally self-supporting and/or self-stabilized or be structurally supported and/or stabilized by:
1) securing it to an adjacent supporting structure;
2) using other methods which provide the required strength and stability;
c) have one or more working platforms and intermediate access platforms;
d) have four or more legs; and
e) have one or more bays.BS 1139-6 pdf download.
BS 1139-6-2022 pdf free downlaod
Note:
If you can share this website on your Facebook,Twitter or others,I will share more.